Skip to content
Ashforte
Case Example — Illustrative

Final account recovery on a rail infrastructure project

A civil contractor completed a metro civils package with significant unresolved variations and claims. The internal team lacked capacity to build the final account under time pressure. Ashforte assembled the account, negotiated close-out and unlocked retention.

Sector
Infrastructure — Rail
Contract
FIDIC Red Book with employer amendments
Scale
USD 240M contract value
Region
Europe
Outcome
Retention released and account settled
Illustrative example — The following are illustrative case studies representing the type of engagements Ashforte is built to deliver. Client identities, project details and figures are anonymised composites drawn from patterns typical to contractor-side commercial and claims work.
Section 01

The situation

The project had reached practical completion 11 months late. A partial EOT had been granted but the associated prolongation, disruption and variation packages had not been consolidated into a coherent final account.

Retention (approximately USD 12M) was being held pending resolution. The Employer's Representative had issued a draft final account materially below the contractor's records, and the internal commercial team had been unable to close the gap through prior negotiation.

The contractor's commercial director engaged Ashforte to build the final account from the existing record base and drive close-out negotiations to release retention.

Section 02

Ashforte's intervention

The engagement was structured around the following workstreams, delivered by a senior-led team operating to Ashforte's standardized delivery protocols.

Phase 01

Account assembly

  • Contract sum reconciliation against as-built quantities
  • Consolidation of prior EOT, prolongation and disruption entitlement
  • Variation register audit and pricing consolidation
  • Set-off and deduction analysis
Phase 02

Substantiation

  • Cost record consolidation for time-related items
  • Correspondence chain reconstruction for variation entitlement
  • Cause-and-effect narratives for prolongation events
  • Evidence pack organisation for negotiation
Phase 03

Negotiation

  • Response to Employer's Representative draft final account
  • Position paper on contested items
  • Without-prejudice discussions across five sessions
  • Escalation triggers documented if settlement failed
Section 03

The result

Final account settlement reached approximately 78% of the contractor's submission value — a material improvement on the Employer's Representative's opening position.

Retention released in full within 90 days of settlement.

The contractor engaged Ashforte on a Portfolio Retainer to prevent recurrence — with particular focus on running variation and change control discipline continuously across live projects rather than consolidating at close-out.

Section 04

Lessons

The lessons from an engagement are usually more transferable than the specific results. What Ashforte's clients typically take away from case studies like this one:

01

Final accounts assembled retrospectively under time pressure lose value that continuously-maintained records would have preserved. The 22% gap between the submission and the settlement was largely attributable to record-base weaknesses rather than positional disagreement.

02

78% recovery was the right outcome given the record base — but the record base was the constraint, not the negotiation.

03

The Portfolio Retainer that followed was specifically structured to run change control and variation discipline continuously — so that the next project's final account is a consolidation exercise, not an assembly exercise.

Service pillar

This engagement sat within Claims & Dispute Support.

Entitlement identified early. Claims built on evidence. Defence positions ready before they're needed.

Explore Claims & Disputes
By Invitation — No Cost

Initial Commercial Risk Assessment

By invitation, Ashforte provides qualified contractors with an initial commercial risk assessment on one live project. A structured senior review of contract, claims and commercial-control exposure, delivered as a documented briefing with a 30-day action plan. Qualification is determined in the first conversation.

A structured review of one live project — offered by invitation, at no cost, to qualified contractors.

Request an initial assessment
What's included
  • 01Review of selected project documents (contract, correspondence, variations, programme)
  • 02Identification of key contract and commercial risk exposures
  • 03Short maturity assessment across notices, variations, claims and payment controls
  • 04A practical 30-day action plan
  • 05Findings call with the project or commercial lead
Typically appropriate for
  • Contractors with active commercial pressure on a live project
  • Variation or claims exposure requiring senior review
  • Payment or certification issues affecting cash
  • Stretched commercial teams needing external senior view
  • Final account or close-out situations